John A. D’Annunzio
Since I started in this industry in 1987 I have been very
consistent in one point: specifications need to be comprehensive so that they
do not lend themselves to contractor interpretation. The reason for this
sentiment is that in the past twenty-five years I have witnessed – or should I
say – I have been an expert witness – in dozens of legal cases where the
specification was open to the contractors’ interpretation. As you can probably surmise,
this rarely ends well for anybody but the lawyers.
The latest case study in this scenario involves an exterior
sealant project on a pre-cast concrete high rise building in the mid-west. The
architect was hired by the Owner to review previously completed exterior
building studies, complete their own investigation of the building and design a
series of remedies that will stop moisture infiltration into the building. The
previous building studies indicated that moisture infiltration was due to openings
at sealant joints at pre-cast panels and windows. The architect relied on these
findings and never completed their own investigation of the building.
Specifications and drawings were completed that indicated
new sealant was required at all buildings joints. The contractor bid the
project, completed the sealant application and was paid for their work. A month
after project close-out leaks developed at corner windows. The contractor
reviewed the leaks and stated that ‘corner tape’ was required and that they had
not completed these joints because they were part of the structural window
frame and did not require sealant. Their claim was that the existing sealant at
these points was improperly applied.
The Owner agreed that ‘corner tape’ was probably the correct
remedy and told the contractor they could progress with this work, but no extra
fee would be paid. This is where the dance started; step one – contractor: this
was not in specification. Step two – owner: we told architect to correct all
exterior issues. Two steps up now one step back: architect: spec and drawings
state to seal all building joints.
The drawings do state to seal all building joints but illustrate
arrows to all building joints except the corner window frames.
Time for the dip in the dance: All parties agree ‘corner
tape’ should be applied. The Owner is willing to pay the Contractor extra for
material but why should they pay rigging costs and labor for joints that were
supposed to be sealed. Shouldn’t this have been in the contract?!
Now we dance again. Step one – contractor: this was not in
specification. Step two – owner: we told architect to correct all exterior
issues. Two steps up now one step back: architect: spec and drawings state to
seal all building joints.
Before the next dip the lawyers may cut in.
This would not have happened with a comprehensive
specification. So I will say in again in 2013: specifications need to be
comprehensive so that they do not lend themselves to contractor interpretation.
No comments:
Post a Comment